Alle plannings- en bouwregelgeving- gerelateerde zaken werden in eigen beheer uitgevoerd

Tunbridge Wells Hospital

Working closely with the client, Ballast Nedam Parking offered a turnkey solution from RIBA Stage 01 to Stage 06. All planning and building regulations related items were completed inhouse saving the client significant additional costs. 

The project was delivered with a keen eye on both price and programme, working to a clear brief to supply a robust and user-friendly solution that requires minimul ongoing maintenance. During the later stages of construction, the Covid 19 outbreak threatened to hamper progress, but our adapted safe systems of working and outstanding site team ensured both programme and budget were maintained.

Project in details

Brief: To design and construct a new deck car park structure over an existing surface car park.
Client: Tunbridge Wells & Maidstone NHS Trust
Construction Period: 8 weeks construction of substructure, steel frame and concrete planks. M&E additional.
Configuration: Circa 320 parking bays. (GF +1)

View as PDF

More information?

Russel Simmons

Managing Director

It gives me great pleasure to introduce this website to you which I hope goes some way to explaining the many benefits in working with us at Ballast Nedam on your car park project.